LIVE CONSTRUCTION DASHBOARD

Patna Metro Construction Progress Tracker 2026

Real-time section-wise construction progress, TBM tunnelling status, girder launching updates, and expected opening timeline for Patna Metro Corridor 1 & 2.

62%
Overall CompletionPhase-1 Construction
6.6 km4 Stations94%

Priority Section (New ISBT → Malahi Pakri)

Trial Run Ready Expected: Mid 2026
2.8 km3 Stations68%

Patna Junction Underground Tunnel

TBM Breakthrough Done Expected: Early 2027
4.2 km3 Stations76%

Danapur → Saguna More Elevated

Girder Launching Expected: Late 2027
3.5 km4 Stations58%

Bailey Road (Zoo → Vidyut Bhawan)

Pier Construction Expected: Mid 2028
3.2 km3 Stations42%

Ashok Rajpath Underground (PMCH → Moinul Haq)

Cut & Cover Method Expected: Late 2028
4.8 km4 Stations35%

Rajendra Nagar → Khemnichak Extension

Land Acquisition Complete Expected: 2029

Construction Milestones Timeline

Jan 2024

TBM "Ganga" launched at Patna Junction

Jul 2024

First elevated viaduct completed at RPS More

Dec 2024

TBM breakthrough at Gandhi Maidan

Apr 2025

Priority section track laying completed

Oct 2025

Signalling & OHE energization (Priority)

Feb 2026

Trial run between ISBT and Malahi Pakri

Aug 2026

Expected: Commercial operations (Priority)

2027

Expected: Patna Junction ↔ Gandhi Maidan open

2028-29

Expected: Full Corridor 1 & 2 operations